We have been busy! The temporary props for the 4 main posts have been removed, along with the tower scaffolds used to guide the purlins into position. The square frame now stands majestic over the levelled chalk platform.
Volunteers have marked out the building footprint. First a baseline datum that runs through the centre of the building was marked out, taking the main post bases as reference. Then the positions of post-hole centres were pegged – using a metre frame/grid.
Our mission is to get the wall posts in the ground before Christmas. The first series of post-holes were augered by machine and the first posts placed in their holes. Initially, this process was relatively straight forward. The base of each hole was measured using a water level (datum marked on each of the main posts at 1000 mm above finished floor level. Each wall post was measured from its base to its tenon shoulder, and this measurement corrected in the base of each hole using layers of tamped chalk. Dry chalk compacts very well using simple stick tampers. Once the desired depth is tamped to a solid base, the post is dropped into position and its tenon orientated with each adjacent peg. Once happy with its vertical (checked with plumb lines in two orientations) the post is tamped into position using dry chalk. The whole process can take anywhere from 30 minutes to 1 hour depending on the problems encountered. The aim is to align the wall posts – ensuring their tenon shoulders are somewhere close to 1000 mm above datum to ensure the easiest wall-plate fit later on!
The water level requires skill to use accurately. The logic being that Neolithic builders had access to water and tubes (in the form of intestines) that could be utilised to ensure levels where required. I feel the use of an accurate level on this Neolithic landscape is demonstrated by the Stonehenge monument which exhibits perfectly level lintel tops, despite each upright being of different lengths in the ground.
Week 11 continued with the installation of the wall posts – although some very wet weather made the task all the harder. Some of the post-holes slumped and we were forced to discover a different method for placing them at the correct level. Some posts were ‘screwed’ into position by attaching a Spanish windlass to them and rotating them with downwards pressure through the thick chalky slurry.
Incredibly, the end of week 11 saw the placement of all 45 wall posts! this is a remarkable achievement for the team and pushes the project on a step further.
Work has commenced on preparing the Oak posts that will form the facade of the building. The facade consists of 6 posts that interact with a single 6 metre lintel. The two largest of these posts are the main door posts – 3300 mm long and around 450 mm in diameter. originally, I had an idea that this facade might be jointed and raised as one complete unit – and although I feel this might be possible, recent weather conditions are curtailing this idea. The heavy rainfall of the last two weeks (and forecast for next week) will adversely affect the ramped post holes we are digging to take these large posts. I cannot risk preparing 6 large holes only to have them slump in heavy rain. I have changed the plan, and now hope to place the two largest door posts, and back-fill them, before we risk digging the next two, and so on.
The positioning of these posts will be the first major lift on the project using person power and simple methods. Nevertheless, adverse weather still has the ability to affect this scaled down operation. In simple terms, we cannot afford to place the posts and NOT immediately tamp them in securely. However, they can only be tamped in with relatively dry chalk to ensure they are secure in the ground.







